Those heavy industry loads vary randomly all day long with caused big voltage fluctuations which can be observed in the 24h voltage curves as illustrated above. The difference between the highest and lowest voltage within a day can reach up to 10% of the nominal voltage, which made the adjacent residential areas suffering every day.
RXPE Solution
The TCR thyristor valves were based on LTT thyristors and designed as vertical layout with water/air cooling method. Redundant circulating pumps and redundant control & protection system were designed to achieve high stability and easy maintenance. SVC major control algorithm was designed as constant voltage strategy to maintain a stable voltage at the 66kV busbar.
RSVG for load compensation of electric arc furnace--Substation of Fujian Hua'an hydropower plant. The 10kV busbar of Fujian Hua'an hydropower plant power development company 35kV Jinshan No.2 substation is connected with four feeders of Yuxing I, II, III and IV for the load of HUAYIXIN iron plant. Yuxing I and II feed two 8000kVA electric arc furnaces respectively, YuxingIII supply one 4000kVA refining furnace, Yuxing IV supply one 630kVA power transformer and 5000kVA reactive power compensation device. In normal production, two EAF and refining furnace will be produced at the same time.
With the rapid development of electrified railway, its influence on power supply and consumption system side is increasingly prominent. Because the railway is a 27.5kV single-phase load, if the balance compensation is not carried out, the voltage of the public access point will be seriously unbalanced, which will have a serious impact on other loads of the network point.